Value Engineering: Process, Function Analysis and Practical Example
Value engineering begins with a practical question: is the cheapest option really the best choice if it consumes more energy, requires frequent maintenance or fails to deliver the required performance?
Consider an office building where two lighting systems meet the initial design requirements. One costs less to install, but the other could deliver greater value over its working life.
In project management, value engineering is not simply about reducing costs. It is a structured approach to understanding essential functions, challenging design assumptions and evaluating alternatives without compromising safety, quality or performance.
This guide explains the value engineering process, introduces function analysis and uses a practical construction example to demonstrate how better decisions are made.
What Is Value Engineering, and What Does Value Actually Mean?
Value engineering is a structured method for improving a project's value by identifying the functions it must deliver and evaluating alternative ways to achieve them. The objective is not to make a design cheaper at any cost, but to deliver required performance reliably and efficiently throughout its useful life.
In practical terms, value depends on three connected considerations: function (what must the element do?), performance (how well must it do it?) and resources (what does delivering that function cost over time?).
A useful conceptual relationship is:
Value ≈ Functional Performance ÷ Resources Used
This is a decision-making principle, not a universal calculation: safety, reliability, functional performance and long-term costs cannot always be reduced to comparable numbers.
For example, substituting a lower-priced component might reduce the initial project budget. But if it requires frequent replacement, increases energy consumption or introduces reliability risks, the apparent saving may weaken overall value.
As the Federal Highway Administration explains, value engineering examines required functions alongside cost, worth and performance to identify better alternatives.
The Value Engineering Process: Six Phases of the Job Plan
Start the value engineering process by defining the decision you need to improve, rather than immediately searching for cheaper materials. The value engineering job plan follows six core study phases, framed by preparation and follow-up. The Federal Highway Administration (FHWA) describes eight phases overall: project selection, six study phases and close-out.
Before the study: Select a project where alternatives could materially improve value. Agree on the scope, performance requirements and constraints, and assemble a multidisciplinary team able to challenge existing assumptions.
- 1
Information (Investigation): Establish the baseline. Review drawings, specifications, budgets, operating assumptions and project risks. Identify high-cost elements and develop a credible baseline using project cost estimation. Output: Agreed requirements, cost baseline and focus areas.
- 2
Function Analysis: Identify what must be achieved. Separate essential functions from supporting ones, then consider each function's cost, worth and required performance. Output: Prioritised functions worth examining.
- 3
Creative: Generate alternatives. Ask how else the same functions could be delivered. Encourage ideas without prematurely screening them for cost or feasibility. Output: A range of potential solutions.
- 4
Evaluation: Screen and compare options. Reject alternatives that fail mandatory safety or performance requirements. Compare credible options against life-cycle cost, practicality and implementation risk. Output: A justified shortlist.
- 5
Development: Test the strongest proposals. Refine designs, validate technical assumptions, estimate costs and assess delivery implications. Output: Documented value engineering proposals with supporting evidence and an implementation approach.
- 6
Presentation: Secure an informed decision. Explain each recommendation, its trade-offs, estimated benefits and uncertainties to decision-makers. Output: A recorded approval, rejection or request for further analysis.
After the study: Implement approved changes, assign responsibility and measure actual outcomes against the baseline. An approved proposal does not itself produce savings: benefits materialise only when the change works in practice.
The purpose of these value engineering steps is not to produce the longest list of ideas. It is to move from a defined function to a defensible improvement decision.
When Should Value Engineering Be Applied?
Apply value engineering as early as practical during concept or preliminary design, when alternatives remain open and changes are less disruptive. It can also support later design reviews or contractor proposals, but redesign costs, approvals and schedule constraints may reduce the benefits. The right timing depends on how much flexibility remains to improve the proposed solution.
Function Analysis and FAST Diagrams: Finding the Right Function
Function analysis shifts value engineering from asking what a component costs to examining what it must achieve. This distinction prevents teams from protecting an existing design when a different solution could deliver the same function more effectively.
Functions fall into two main categories:
Basic Functions:
The essential purpose a system must fulfil. For an office lighting system, this is Illuminate Workspace.
Secondary Functions:
Supporting functions, such as Control Glare or Adjust Brightness. Some are necessary to meet performance requirements; others depend on the chosen design.
Describe each function using a verb–noun combination, rather than naming equipment. This separates the required outcome from the technology used to achieve it.
Function Cost represents the resources currently allocated to delivering a function. Function Worth is an informed estimate of the minimum resources needed to achieve that function to the required standard, based on feasible alternatives. Comparing the two helps identify opportunities for improvement without compromising essential performance.
How Does a FAST Diagram Support Function Analysis?
The Function Analysis System Technique (FAST) maps relationships between functions through two questions: How? and Why?
For example:
Illuminate Workspace → Distribute Light → Direct Light
Secondary Functions
Reading rightwards explores how a function is achieved; reading leftwards tests why each supporting function is needed.
Unlike a project schedule, a FAST diagram shows functional logic, not the order of activities.
As explained in SAVE International's Function Analysis Guide, this approach helps teams challenge assumptions and identify alternatives before comparing their costs.
Value Engineering in Construction: A Worked Project Example
Value engineering in construction is most useful when a project team can compare different ways of delivering the same essential function. Consider an office building whose lighting specification is being reviewed before construction begins. The objective is not simply to buy cheaper fittings, but to provide reliable lighting at a defensible whole-life cost.
Define the Required Function and Compare Alternatives
The basic function is Illuminate Workspace. Before comparing prices, the team establishes what an acceptable solution must achieve: appropriate illumination for office tasks, electrical safety, glare control, reliable operation and maintainable equipment.
Two LED solutions are proposed:
Option A — Standard LED system: Lower installation cost, with conventional controls and higher forecast energy and maintenance expenditure.
Option B — Higher-efficiency LED system: More expensive initially, with zoned controls intended to reduce operating costs.
Both proposals must satisfy the same performance criteria. If either fails essential requirements, it should be rejected before financial comparison.
Compare Life-Cycle Costs and Make the Decision
The team estimates initial expenditure and five years of energy and maintenance costs.
Illustrative assumptions: The example considers a 2,000 m² office building operating its lighting for 3,000 hours annually, with electricity priced at £0.20/kWh. Estimated annual consumption is 42,500 kWh for Option A and 22,500 kWh for Option B. Maintenance costs are illustrative annual estimates, not supplier quotations.
The five-year totals are calculated as initial cost + five years of annual energy and maintenance costs. Option B requires £12,000 more upfront, but its projected annual operating costs are £5,500 lower.
This produces two useful findings:
Five-year cost difference: £94,500 − £79,000 = £15,500 in favour of Option B.
Simple payback: £12,000 ÷ £5,500 = approximately 2.18 years.
Under these assumptions, Option B offers the lower five-year cost.
Discounted cost comparison: Using a 5% annual discount rate and assuming operating costs occur at each year-end, the five-year present cost is approximately £86,923 for Option A and £75,111 for Option B. Option B retains an estimated £11,812 advantage. This remains a simplified comparison, excluding potential replacements, residual values and changes in operating conditions.
The US Department of Energy's guidance on building life-cycle costs explains why alternative building systems should be evaluated beyond their purchase prices.
Before recommending Option B, the team must verify illumination performance, electrical compliance, maintenance assumptions and the practicality of its controls. A higher initial investment creates value only when the promised function and long-term benefits are credible.

Value Engineering vs Value Analysis: What Is the Difference?
Value engineering vs value analysis is primarily a distinction of when the methodology is applied, rather than what it aims to achieve. Both seek to improve value by examining required functions and identifying better ways to deliver them.
Value Engineering (VE)
Typically applied during design or before implementation.
Improves alternatives before major decisions are finalised.
Value Analysis (VA)
Typically applied to existing products, systems or processes.
Reassesses established solutions to improve performance or cost.
Consider our office lighting example. Comparing LED systems before installation is a typical value engineering activity. Reviewing an existing lighting system to reduce operating costs would more commonly involve value analysis.
However, this distinction is not absolute. SAVE International recognises both within the broader Value Methodology, and their practical applications can overlap.
How to Approve and Implement Value Engineering Recommendations
Value engineering analysis becomes valuable only when a proposed improvement survives technical scrutiny, receives appropriate approval and delivers measurable results.
Before accepting a recommendation, project managers should apply five decision checks:
- 1
Confirm mandatory requirements. Reject proposals that fail safety, regulatory, contractual or essential performance standards. These are pass-or-fail conditions, not factors to offset against cost savings.
- 2
Compare whole-life costs. Assess initial expenditure, operation, maintenance and replacement assumptions consistently. A lower purchase price alone cannot establish better value.
- 3
Examine delivery risks. Consider design changes, supplier availability, technical approvals, installation complexity and potential schedule disruption.
- 4
Assign decision ownership. Establish who can authorise the change, who will implement it and what evidence supports the recommendation. For several compliant alternatives, a weighted decision matrix can make trade-offs transparent.
- 5
Verify actual performance. Record the approved baseline, expected benefits and review dates. Use appropriate project controls to compare realised costs and performance against the original assumptions.
For the office lighting example, the project team should approve Option B only after validating its technical suitability and projected operating savings.
A recommendation is not a realised benefit. Its value becomes credible when the approved change is implemented and its outcomes are verified.
Develop Practical Value Engineering Capability with LOTC
Value engineering is not about choosing the cheapest option. It is about making better decisions on how essential functions are delivered throughout a project's life.
Turning that principle into practice requires the ability to analyse functions, lead structured studies, evaluate alternatives and assess life-cycle costs before committing resources.
The Value Engineering Essentials programme builds these foundational capabilities, while Advanced Value Engineering supports professionals managing more complex studies and decisions.